Ending coverage properly matters: until you file the NOT, you are still the responsible operator. Here is how and when to close out.
Filing your Notice of Intent starts your permit coverage. Filing your Notice of Termination (NOT) is how you properly end it, and skipping it is a quiet but costly mistake, because until you terminate, you are still on the hook for the permit.
The NOT tells TDEC that your construction is complete, the site is stabilized, and you are ending coverage under the Construction General Permit (TNR100000). Like the NOI, it is filed through the MyTDEC portal.
Answer a few questions about your site and get a field-ready SWPPP built to TDEC permit TNR100000, ready to review, sign, and submit.
Get startedYou file the NOT once the site has reached final stabilization, meaning disturbed areas are permanently stabilized (for example, established perennial vegetation providing dense cover, or permanent hard surfaces), and construction activity is complete. Temporary cover or a mostly-done site is not enough; the standard is final, permanent stabilization.
After the site reaches final, permanent stabilization and construction is complete. It is filed through MyTDEC to end your CGP coverage.
You remain the permitted operator, still responsible for inspections and permit conditions, and an open permit on a finished site can be flagged during an inspection.
Permanent stabilization of disturbed areas, such as established perennial vegetation with dense cover or permanent hard surfaces. Confirm the exact standard in the current permit.